Some of the things we’ve accomplished during the last two years
- Building
- Painted the outside front of the building and rear steps
- Replaced decaying steel ramp at east side front entrance with cement ramp and new railing & installed cement base for re-location of WW I – mortar launcher
- New outdoor carpet for front entrance
- HVAC maintenance & repairs
- Lobby doors – replace locks and relocate alarms
- Converted upstairs cloakroom into large storage space
- Repainted parking lot lines
- Members’ lounge
- Painted both lounges & halls
- Upgrades to lighting & electrical in members’ lounge
- reframed pictures
- refinished bar
- Sports lounge
- Pool Tables refurbished
- New dart boards, backing & carpet installed
- New 85” tv
- Kitchen
- Plumbing repairs to kitchen sink
- repairs to Hobart dishwashing system
- new refrigerator
- Temporary Front yard Summer Patio established for COVID & application for permanent front yard patio submitted
- Successfully applied for various government grants including a Trillium Grant for COVID relief
- Negotiated a 3-year rental agreement for our second floor with a community Group
- Established a Branch 154 website, “caledonialegion154.ca”, to improve communication with members and the community